Seabed Separation has been invited by several oil companies to participate in several case studies together with various engineering companies.

The table below is an example on such.

Unfortunately, none of these projects have been follow up due to commercial aspects.

The table shows that the interest for the DPS technology is a mix of Norwegian operators as well as international oil companies. The projects span from normal shallow water installation to deep water fields.

The DPS technology has an advantage on the deep-water fields due to its pipe design easy adaptable to high external pressure.

Operator Field Description
AkerBP Vilje/Skogull Concept study together with Subsea 7
Alvheim Greater Area development. Concept study headed by AKSO with assistance from Subsea 7 and Seabed Separation
Lundin Rolvsnes A DG 1 study produced and extended well test ongoing. The EWT results will be the trigger to install the DPS system. Rolvsnes host cannot receive the formation water due to H2S.
WintershallDEA Nova DG 1 study performed. Production start up delayed 23/24 which influence start of DPS DG2 study.
OKEA Draugen Concept study how to separate produced water at seafloor from the North and the South area prior to injection in an old oil producer
Jette Concept study on the JETTE field with tie back to YME. Involved subsea tie-in of two adjacent reservoirs. Reinjection of separated water
Petronas Abu-Enau DG 2 study performed by AKSO, FAST subsea and Seabed Separation. Project put on Hold due to uncertainties regarding well performance
Bestari In cooperation with FAST subsea present a solution to separate the water for reinjection and use the FAST pump to increase the IOR. Involvement by AKSO in KL.
CW-Icon Together with AKSO presented a deep water solution for two different cases. Separation and reinjection of produced water. Long tie back and cold environment
DBO Brasil Gondolfo Proposal to develop the Gondolfo field by instaling the DPS unit to separate water from one well to be able to drill and tie-in a new well Riser constrictions.
Equinor Norne Presented a proposal to tie-in some discoveries on the NORNE field using existing infrastructure
Åsgard Gas condensate field with high volumes of water in the well stream. Evaluated separating the water from the condensate to avoid flooding of the Åsgard gas compression station. Equinor still studying solutions on how to solve the problem